Major AWACS upgrade set to begin

  • Published
  • By Patty Welsh
  • 66th Air Base Group Public Affairs
The next step in the largest block upgrade in the history of the Airborne Warning and Control System is set to occur today at Tinker Air Force Base, Okla., when the first aircraft receiving the block 40/45 modification is inducted by the Oklahoma City Air Logistics Center.

"This modification replaces a mission computer system originally installed in the 1970s," said Maj. Brett Johnson, AWACS 40/45 Production chief. "The new system will have an open, network-based architecture, enabling future net-centric modifications."

New mission software will enhance tracking and combat identification capabilities, in addition to providing operators with a better picture of the battlespace.

The upgrade also allows for more sensor integration both on- and off-board the aircraft, improves the aircraft's data link infrastructure, improves machine-to-machine interaction and compresses the kill chain timeline.

"Think about technology thirty or forty years ago, or even five years ago, and compare it to the capabilities a smartphone has today," said Major Johnson. "We need to give our warfighters improved technological capabilities so they can do their jobs more efficiently and effectively."

The upgrades are being performed at the same time as programmed depot maintenance to minimize aircraft operational downtime.

"Doing a modification of this size during PDM has never been done before," said Major Johnson. "The scheduling, planning and coordination has been a key piece to get us to this event."

Seeing how successful the planning has been, other program offices are expressing interest in trying to do something similar for their modification efforts.

While the Oklahoma City Air Logistics Center will perform the upgrades, the Electronic Systems Center is the lead integrator.

In late October, ESC awarded a contract to Boeing for $65 million to procure and manage the thousands of parts needed and also provide on-site production and installation support throughout the upgrade.

"ESC's role as lead integrator is to ensure all the pieces are in place so, before a wrench is turned, everything needed is there," said Major Johnson.

This first aircraft is the centerpiece of Low Rate Initial Production, he continued.

Modifications to the first aircraft are scheduled for completion by September 2011. During LRIP, six aircraft are scheduled to be upgraded by 2014.

"This first aircraft is critical," said the major. "It puts us on the path to our full rate production decision, which is planned for 2012."

All the aircraft in the U.S. AWACS fleet are scheduled to be at full operational capability by 2020.

As a significant amount of the equipment being installed is commercial-off-the-shelf, ESC members are also thinking ahead about technology obsolescence.

"Anyone who has bought a laptop computer over the last few years knows how quickly technology can change," said Major Johnson. "We're replacing all of the onboard computer work stations with laptops over the next several years, one aircraft at a time. In a modification of this complexity, laptops are only one of many components we are carefully watching."

To accomplish that, ESC awarded a contract to Boeing for $15 million in September to support active management of diminishing manufacturing sources and materiel shortages.

"There are a lot of moving parts and a lot of interdependencies to this upgrade," said Major Johnson. "It has taken a lot of people from ESC, OC-ALC and Boeing to keep us on the right track."